Laying with and without substructure - step by step guide

Variant 1: Laying with substructure without geotextile

Create ballast base layer

Create a 15-20 cm high gravel base layer (grain size 0-32 cm) directly on the topsoil. In the case of soils with poor bearing capacity, reinforce the base layer with 15-20 cm to 30-40 cm.

Chippings levelling and connecting ground grids TERRA GRID E 35

If necessary, apply 2-3 cm of chipping levelling (grain size 2-5 mm).

Insert the slabs with the closed side face down and snap them into place by using your foot on the existing layer

Backfilling ground reinforcement with sand or gravel

Cover the entire surface area with approx. 2-4 cm with coarse sand or gravel.

Finished driveway with ground reinforcement grids TERRA GRID E 35

The floor is now stable and ready.

Variant 2: Laying with substructure with geotextile

Geotextile Rogeo 200 under the base layer

Apply a layer of geotextile (fleece Rogeo 200) on the existing soil. At the same time, increase the load-bearing capacity on the poorly load-bearing soils without using additional base layers.

Crushed stone base layer for TERRA-GRID E 35 ground reinforcement

Apply a 10-15 cm high gravel base layer (grain size 0-32 cm).

Installing TERRA GRID E 35 ground grid in landscaping

Make 2-3 cm of chippings levelling (grain size 2-5 mm) and lay TERRA-GRID E® 35 on top with the closed side face down. Insert each slab by using your foot to snap them into the existing layer.

Backfilling TERRA-GRID E 35 ground grid in landscaping and civil engineering

Cover the entire surface area with approx. 2-4 cm round gravel (2-8 mm) or chippings/trash.

Finished ground reinforcement for parking space with TERRA-GRID E 35 ground grid

The floor mounting is now stable with optimal load distribution without sealing.

Click here and get your non-binding offer

Laying without substructure

Connecting and aligning TERRA-GRID E 35

Place the first TERRA-GRID E® 35 panel directly on the existing floor with the closed side facing upwards and aligned.

Connecting ground grids

Snap each additional panel into place by using your foot on the existing layer.

Rolling in TERRA-GRID E 35

Ground grids are worked into the turf with a roller, tamper, or vibratory plate.

Finished parking lot with ground grids TERRA GRID E 35

So easily and quickly you have produced a stable surface without substructure with TERRA-GRID E® 35.